Spoke to SS today and he mentioned the downpipes still need to be painted :-)
What a relief...
The blog is dedicated to our building experience in Featherbrook Estate Point Cook, Victoria Australia.
Wednesday, 2 November 2011
Tuesday, 1 November 2011
Wrong color downpipes
We went to the house today and the plaster is almost completed. The kitchen hasn't delivered has SS mentioned earlier. But we also noticed all the downpipes are different color.
We have asked for Jasper color downpipes same as our colorbond roof. Here is the picture of what is currently installed.
The skirting work still need to be completed. Hopefully all gets done by end of this week.
We have asked for Jasper color downpipes same as our colorbond roof. Here is the picture of what is currently installed.
The skirting work still need to be completed. Hopefully all gets done by end of this week.
Monday, 31 October 2011
Some more photos...with plaster
Plaster started on 24/10 and we went to see the house on 25th. So much was done in two day. Very impressed with the quality and the progress so far. We haven't been to the house in last 5 days and it happened first time since the house started to build. Will put some more photos soon with the progress report.
I was told that Kitchen will be delivered today and installed this week. Looks like when we go next time which will be on Wednesday, the kitchen & plastering will be completed.
Front View of the house
Entrance & Garage door
Study
Study
Master Bedroom Entrance
Kitchen & Family Room
Dinning & Theatre Room
Full view of the Kitchen & WIP
Games Room
BedRoom 4
Bedroom 3
Toilet
Laundry
Alfresco
Entrance with temporary door
WIP
Master Bedroom
Ensuite - Spa
Formal Lounge
Thursday, 27 October 2011
Plaster Started on 24/10/2011
Spoke to the SS and he mentioned that plaster will be starting from 24/10. Went to the house during the weekend and saw all the plaster material delivered in the house.
26/10/2011 - Went to the house yesterday and saw the plaster on all the walls, looks it will be completed by end of this week. SS mentioned that the kitchen will be delivered and install by next week..
Will put some more photos here soon.
All is going well so far..will be arranging an external company to do the pre-handover inspection.
According to the SS the house will be completed in Jan 2012 but the way all is going, I am sure they will complete it before the Christmas break. Hoping for the best...
26/10/2011 - Went to the house yesterday and saw the plaster on all the walls, looks it will be completed by end of this week. SS mentioned that the kitchen will be delivered and install by next week..
Will put some more photos here soon.
All is going well so far..will be arranging an external company to do the pre-handover inspection.
According to the SS the house will be completed in Jan 2012 but the way all is going, I am sure they will complete it before the Christmas break. Hoping for the best...
More Photos...
Before the land release
Building work started on 01/09/2011
Slab done on 09/09/2011
Frame work started ...
Some of the photos