Friday 11 November 2011

Kitchen Installed

We went to see the house yesterday afternoon and the kitchen was delivered and installed, also the laundry, WIP, bathroom, Ensuite cabinets are installed.
Will post some photos soon. Now the paint will start from next week (hopefully) 

Plaster & Skirting will be completed by Friday 04/11/11 - COMPLETED
Kitchen delivered and installed – 5 days by 11/11/11 – COMPLETED
Bathroom & laundry cabinet – 2 days – COMPLETED
Electrician – 5 days
Plumbing – 2 days  
Paint – 3 days
Tile & carpet – 5 days
Laminate flooring – 3 days